There will be a "work bee" this Saturday at 11am. We are waiting on contractors and electricians before we can paint rooms, or put down carpet or baseboards. Here is what we can do this Saturday, please let me know if you can help with these specific tasks:
1. Removal of three toilets: there are two baths in the worship center, 1 in kid's bath
2. Using a power lift to take down a lot of ceiling tiles in the "lobby"
and a few in each of the classrooms. (maybe we could use a very tall ladder for the classroom ceilings?)
3. Using the lift to paint the metal seams of that drop ceiling (after old tiles are removed)
4. Removing all plastic outlet covers in each room (keep track so we can replace them with white)
5. Changing out some actual outlets from red or tan to white
6. Removing old vinyl baseboard
7. We have some walls that need to "prepped" for painting with putty and sanding.
8. Several light bulbs to be changed in 1st-5th grade classroom
9. Prayer Suite: Paint window and door frames white. Replace some ceiling tiles
10. Hallway: remove signs from doors
UPDATE: Tomorrow at 11am we will meet to get the party started! There are a couple additional tasks we can try to cover tomorrow:
- Bathrooms to be cleaned
-Take down DJ stand in student center
-Fill in holes, sand and Paint main wall in Office/student center
-lots of screws to remove and holes to fill in the counseling/prayer rooms
(power screwdrivers/drills would be helpful to bring with you)
If you are able to help tomorrow, please try to bring some of your own tools for your tasks (if you have them- don't go and buy anything)