There will be a "work bee" this Saturday at 11am. We are waiting on contractors and electricians before we can paint rooms, or put down carpet or baseboards. Here is what we can do this Saturday, please let me know if you can help with these specific tasks:
1. Removal of three toilets: there are two baths in the worship center, 1 in kid's bath
2. Using a power lift to take down a lot of ceiling tiles in the "lobby"
and a few in each of the classrooms. (maybe we could use a very tall ladder for the classroom ceilings?)
3. Using the lift to paint the metal seams of that drop ceiling (after old tiles are removed)
4. Removing all plastic outlet covers in each room (keep track so we can replace them with white)
5. Changing out some actual outlets from red or tan to white
6. Removing old vinyl baseboard
7. We have some walls that need to "prepped" for painting with putty and sanding.
8. Several light bulbs to be changed in 1st-5th grade classroom
9. Prayer Suite: Paint window and door frames white. Replace some ceiling tiles
10. Hallway: remove signs from doors
-Has anyone used a floor grinder on concrete? or sealed a concrete floor?
-Could anyone take over the Children's bathroom remodel? This can be done any time between 1/15 and 1/30
Paint walls
replace a toilet
install of vinyl flooring (over cement)
replace pedestal sink and faucet (possibly mirror)
- I can help with #4, the outlets and #9 painting in the prayer suite. Paula
- I cannot help Saturday but I will be able to help several afternoons this week after 330